Installing pipe lines & pump motors in molasses pump house
Lime house showing the concret slab
Placing floor reinforcing under the granulator at col. 125 - 225 - 228 - 128 bay
Powerhouse switch board in place
Molasses pump house finishing room
Installing rock catcher in beet pumphouse
Installation of catchall & condenser piping at the pan floor
Main building showing scaffolding removed
Interior view gas reducing station
Front view of intercampaign heating boiler
Finishing topping on cutter floor
Sulphur bin and pattern platform steel
Crystallizers showing platform & stairway under construction
Picking table floor showing picking table under construction
Cutter floor showing motor bases in place, conduit being installed and reinforcing in place
First floor wall partitions ready for plastering
Placing transite on warehouse
Canopy steel erected and rivetting about completed
Looking east at rear of the heating and main boilers
Laying vermiculite on the west end of sugar warehouse
Erecting sugar warehouse canopy steel
Installing conduit for powerhouse machinery
Wiring No. 26 Cabinetrol pulp warehouse
Welding roof on oil storage tank
Piping under carbonation tanks
South side of first floor showing giproc [gyprock] lath and hyrib [Hy-Rib] lath
Placing vermiculite on the power house roof
Looking north-east at beet end juice pumps and piping
No. 2 boiler insulation completd on side walls
Southwest corner of pulp warehouse showing bag conveyor and heaters platform
Excavation for No. 9 track and footings for warehouse canopy
Forming for office steps
Finishing topping office second floor
Plastering monitor parapet wall
Installation of tile refractory No. 2 boiler
Placing rafters on No. 1 molasses storage tank, No. 2 ready for testing
Front view of main building
Molasses tanks in course of erection
Pouring first lift of lime house walls
Placing under-floor conduits for switchgear and control panels
Office basement showing plumbing and heating piping being installed
Roofing on main building proceeding; pouring 6th lift sugar end
Lime house steel nearing completion
Piping under evaporators
Pouring last lift of main building
Steam generator No. 1 showing gas bruner opernings and super-heater headers
Pulp dryer furnace brick work proceeding
Beet end juice pumps in place on bases
Structural steel for lime kiln tower nearing completion
Lifting No. 2 boiler breeching in place; fuel oil tank footings in foreground