- AM1592-S8-2-F02-: 2011-092.6874
- Item
- Feb. 16, 1949
Showing 1911 results
Archival descriptionForming first lift of pulp drier walls
- AM1592-S8-2-F02-: 2011-092.6873
- Item
- Feb. 9, 1949
Beet end showing addition of two trusses, second carbonation tank, one Oliver filter
- AM1592-S8-2-F02-: 2011-092.6872
- Item
- Feb. 9, 1949
Backfilling of power house completed
- AM1592-S8-2-F02-: 2011-092.6871
- Item
- Feb. 2, 1949
Beet end showing addition of one truss and foam stacks to carbonation tank
- AM1592-S8-2-F02-: 2011-092.6870
- Item
- Feb. 2, 1949
Welding top cover of Dorr tank
- AM1592-S8-2-F02-: 2011-092.6869
- Item
- Feb. 2, 1949
Completion of pulp drier structural steel
- AM1592-S8-2-F02-: 2011-092.6868
- Item
- Feb. 2, 1949
Applying waterproofing to generator pit walls and backfilling foundation wall of main building
- AM1592-S8-2-F02-: 2011-092.6867
- Item
- Jan. 26, 1949
Beet end showing addition of the first two carbonation tanks and one Oliver filter
- AM1592-S8-2-F02-: 2011-092.6866
- Item
- Jan. 26, 1949
Placing a cyclone in the pulp dryer plant
- AM1592-S8-2-F02-: 2011-092.6865
- Item
- Jan. 26, 1949
View of blacksmith shop showing boom extension for Orton crane being fabricated
- AM1592-S8-2-F02-: 2011-092.6864
- Item
- Jan. 26, 1949
Second floor steel & Dorr tank fabrication
- AM1592-S8-2-F02-: 2011-092.6863
- Item
- Jan. 19, 1949
Looking north at factory garage
- AM1592-S8-2-F02-: 2011-092.6862
- Item
- Jan. 19, 1949
Assembling of pit dryer cyclones
- AM1592-S8-2-F02-: 2011-092.6861
- Item
- Jan. 19, 1949
Powerhouse foundation wall, generator pit and generator foundation
- AM1592-S8-2-F02-: 2011-092.6860
- Item
- Jan. 19, 1949
Beet end showing No. 1 Oliver, Dorr tank, & #3 first carbs tank
- AM1592-S8-2-F02-: 2011-092.6859
- Item
- Jan. 19, 1949
Pouring generator pit walls and foundation wall between main building and powerhouse
- AM1592-S8-2-F02-: 2011-092.6858
- Item
- Jan. 12, 194
Assembling of pulp dryer cyclones
- AM1592-S8-2-F02-: 2011-092.6857
- Item
- Jan. 12, 1949
Looking east showing erection of Dorr tank and structural steel
- AM1592-S8-2-F02-: 2011-092.6856
- Item
- Jan. 12, 1949
Bottom of Dorr tank on location and welded
- AM1592-S8-2-F02-: 2011-092.6855
- Item
- Jan. 4, 1949
Pulp dryer in place on trunnion, structural steel being completed
- AM1592-S8-2-F02-: 2011-092.6854
- Item
- Jan. 4, 1949
Diesel oil tank storage erected at left and completed
- AM1592-S8-2-F02-: 2011-092.6853
- Item
- Dec. 29, 1948
Beet end steel erected to date
- AM1592-S8-2-F02-: 2011-092.6852
- Item
- Dec. 29, 1948
Rolling pulp drier drum off flatcar
- AM1592-S8-2-F02-: 2011-092.6851
- Item
- Dec. 20, 1948
Pouring slab of Dorr Tank foundation
- AM1592-S8-2-F02-: 2011-092.6850
- Item
- Dec. 21, 1948
Looking north in cupola of bulk storage bins at installation
- AM1592-S8-2-F02-: 2011-092.6849
- Item
- Dec. 15, 1948
Looking north from 03 column line at Dorr Tank foundation
- AM1592-S8-2-F02-: 2011-092.6848
- Item
- Dec. 15, 1948
Outfall of waster water line showing rip rapping & revertment
- AM1592-S8-2-F02-: 2011-092.6847
- Item
- Dec. 8, 1948
Forms for foundation wall of gas reducing station
- AM1592-S8-2-F02-: 2011-092.6846
- Item
- Dec. 8, 1948
Footings for walls of generator
- AM1592-S8-2-F02-: 2011-092.6845
- Item
- Dec. 8, 1948
General view of factory from scale house road
- AM1592-S8-2-F02-: 2011-092.6844
- Item
- Dec. 1, 1948
Structural steel to 06 column line forming Dorr Tank foundation
- AM1592-S8-2-F02-: 2011-092.6843
- Item
- Dec. 1, 1948
Pouring footings for gas reducing station
- AM1592-S8-2-F02-: 2011-092.6842
- Item
- Dec. 1, 1948
Completing turbo-generator foundation and starting generator pit footings
- AM1592-S8-2-F02-: 2011-092.6841
- Item
- Dec. 1, 1948
Applying the roofing to the factory garage
- AM1592-S8-2-F02-: 2011-092.6840
- Item
- Nov. 24, 1948
Calandria with cone bottom in place (Taber pans)
- AM1592-S8-2-F02-: 2011-092.6839
- Item
- Nov. 22, 1948
Calandrias for Taber pans in refinery plate shop, Vancouver
- AM1592-S8-2-F02-: 2011-092.6838
- Item
- Nov. 22, 1948
Bottom core and charge ring for Taber pans fabricated in refinery plate shop, Vancouver
- AM1592-S8-2-F02-: 2011-092.6837
- Item
- Nov. 22, 1948
Frost fence and wet hopper superstructure
- AM1592-S8-2-F02-: 2011-092.6836
- Item
- Nov. 24, 1948
Completing foundation wall forms between columns
- AM1592-S8-2-F02-: 2011-092.6835
- Item
- Nov. 24, 1948
- AM1592-S8-2-F02-: 2011-092.6834
- Item
- Nov. 17, 1948
General view of waste water lines from builk storage bins
- AM1592-S8-2-F02-: 2011-092.6833
- Item
- Nov. 17, 1948
Forming foundation wall between power house & main building
- AM1592-S8-2-F02-: 2011-092.6832
- Item
- Nov. 17, 1948
General view of beet pumphouse & main flume
- AM1592-S8-2-F02-: 2011-092.6831
- Item
- Nov. 17, 1948
Frost fence & piling ground from east end of #3 flume
- AM1592-S8-2-F02-: 2011-092.6830
- Item
- Nov. 17, 1948
Boiler foundation being stripped and backfilled
- AM1592-S8-2-F02-: 2011-092.6829
- Item
- Nov. 10, 1948
Pulp warehouse from the southeast
- AM1592-S8-2-F02-: 2011-092.6828
- Item
- Nov. 10, 1948
Rivetting the wet hopper superstructure
- AM1592-S8-2-F02-: 2011-092.6827
- Item
- Nov. 10, 1948
Backfilling and stripping the main flume
- AM1592-S8-2-F02-: 2011-092.6826
- Item
- Nov. 10, 1948
Main flume from beet pumphouse on left to main building at right
- AM1592-S8-2-F02-: 2011-092.6825
- Item
- Nov. 3, 1948