Pouring slab at Waste Water Pump House. Looking south
- AM1592-S8-2-F01-: 2011-092.6579
- Item
- May 31, 1948
Pouring slab at Waste Water Pump House. Looking south
Erecting a leg at a rigid frame bent.
Looking north at forming for foundation walls of waste water pumphouse
Plywood forms for exterior face of pulp warehouse walls
General view of of interior of pulp warehosue looking east along temporary track
Using pneumatic tamper to compact base for machine shop floor
Installing fixtures in storeroom
Pouring Vermiculite fill on roof of Sugar Warehouse
Erecting the first lift forms at the west end of the Pulp Warehouse
Forming slab of the reservoir section fo the Waste Water Pump House
Interior view of west end of pulp warehouse showing forms ready for first lift pour
View of completed framework of pulp warehouse from east
Wet and soaking hoppers with piling area in background
View from machine shop showing west wall stripped and backfilled
Setting up forms and mixing plant preparatory to raising the chimney
Moving shop tools into Machine Shop
Looking west along grade for Tracks 1, 2 & 3
Reinforcing in place for slab of reservoir at waste water pumphouse
General view showing first & second lift forming of pump warehouse walls, chimney in foreground
Manhole E being set, and locomotive house footing forms in place across road
West end of pulp warehouse showing Truck bin supporting steel and conveyor tunnel forming
Fifth lift on chimney being erected by Rust Engineering Co.
View of bulk storage bins from the west, showing the windows and flashing installation
Pouring floor at waste water pumphouse
Foundation walls of waste water pumphouse and forming walls of reservoir section
Chimney at elevation 127'-6" above base
Laying blocks and installing door frame of locomotive shed
Looking southeast from top of bins, showing chimney erection and formwork on walls of pulp warehouse
Air view of factory site, looking northwest
Air view of factory site, looking south
Finishing touches being put on chimney
Pouring walls of reservoir section of the pumphouse, looking northeast
West end of machine shop and storeroom
West end of pulp warehouse showing first lift stripped
Excavation for foundations of packing house from top of sugar warehouse
Pouring west end third lift of pulp warehouse
Completed foundations of waste water pumphouse
Laying brick at waste water pumphouse
South wall forms for packing house
Setting the form for conveyor pit #4 in pulp drier building
Packing house foundations from top of machine shop
General view showing roofing proceeding on pulp warehouse