Interior view of beet end wall forms showing arrangement of scaffolding
- AM1592-S8-2-F02-: 2011-092.6951
- Item
- June 1, 1949
538 results with digital objects Show results with digital objects
Interior view of beet end wall forms showing arrangement of scaffolding
Sugar end steel from top of bulk storage
South elevation of pulp drier & main building
Pouring anchor blocks on wet hopper water line, laying tile for pulp warehouse roof drains
Forms for office foundation walls
Forms for limerock unloading ramp in foregraound & installing windows in boiler house
Front view of factory showing fourth lift forms on beet end walls and second lift stripped
Forming office building foundation walls
Interior of boiler house showing foundations of No. 1 & inter-campaign boiler
View of second floor from behind sulphur tower showing assembly of standard liquor heaters
General view from top of bulk storage showing transite completed
West elevator from factory site gate
Looking east at beet end of main building showing first lift stripped and third lift being erected
Sugar end showing addition of "B" pan
General view of power & boiler house showing transite on roof of boiler house
South side of pulp warehouse showing excavation & backfilling of trenches for roof drains
Looking south along beet flume water line at value for No. 2 flume
Looking west from top of the pulp warehouse
Looking northwest at boiler house & gas reducing station at right
Erecting monitor steel for sugar end of main building
Pouring second lift of main building walls
Overflow pond at waste water pump house
Looking south from west side of machine shop at second & first carbonation station piping
Completing forms for the last lift on the boiler house walls
Installing transite siding on wet hopper superstructure
"A" pan installed & "E" being installed
North elevation of pulp drier building showing completed window installation
South elevation of power and boiler house walls showing completed power house walls
Third lift wall forms being erected for power and boiler house
Installing glass blocks in north wall of pulp drier building
Forming third lift walls on power & boiler house
Substation at waste water pumphouse
Excavating for water line to beet flumes
Main building steel from bulk storage bins
Second lift walls nearing completion - boiler house
Pulp drier walls from the south
Pulp drier building, 1st lift form stripped
Boiler house structural steel with 1st forms in place
Boiler house structural steel complete
General view front of plant - looking east
Main building structural steel from bulk storage
Pouring first lift of power & boiler house walls