A complete pier [bridge support]
After [south end of Granville Street Bridge with traffic, looking north]
Before [view of Granville Street, False Creek and North Shore looking north]
Curing and patching the deck [men paving bridge deck]
Excavation for footing of a pier [men working in excavation pit]
Excavation for pier M7. Floating clamshell dredge and scow
Finishing the deck [construction of bridge ramp deck]
Foreground - a plinth of a pier is stripped and ready for shaft steel [bridge support construction]
Forms for the deck [men working on bridge deck]
From the air [aerial view of Vancouver and False Creek showing Burrard and Granville Street bridges]
Granville Bridge construction project sign on site
Ground-breaking ceremony (dignitaries seated)
Junction of 4th [Fourth]/Fir [Street] ramp and Granville [Steet] south [view from ground]
Looking down into the cofferdam [bridge support construction (detail)]
North end and Howe Street ramp [panorama of bridge construction]
Pier M6 complete and stripped [bridge support construction looking west]
Pouring the deck [pouring concrete for bridge deck]
Reinforcing steel for the deck [construction of rebar support for bridge deck]
Runways and 'motobuggies' to carry the concrete for the deck [construction of bridge ramp deck]
Seymour Street ramp [view of bridge ramp supports from ground]
Steel closure at pier M1 [installation of steel support beam]
Steel closure to pier M6 [construction of steel deck truss, mid span]
Steel closure to pier M7 [construction of steel deck truss]
Steel work at pier M6
Structural steel for the deck [steel support for bridge deck]
The cofferdam of pier M7 [pile driving, north side]
The collapse of M6 cofferdam [B.C. Bridge & Dredging Company dredger, Granville island]
The completed deck with centre curb and traffic lines [mid span looking north]
The curved beams between S-35 and S-36 on the Hemlock [Street] ramp [view of bridge ramp supports from underneath]
The dream
The first steel member in place from pier M8 to falsework bent [bridge support construction]
The form for the footing [foundation construction]
The [Granville Bridge] opening ceremony [mid span]
The new and the old [view of new and old Granville Street bridges, looking north]
The piers on Granville island ready for the steel work [bridge supports looking south]
The prefabricated shaft steel erected on the plinth ready for forming
The problem [old (second) Granville Street Bridge with swing span open]
The roller bearings and wind girder are in place on M7 ready for the steel
The shaft of pier M7 being built in the cofferdam [bridge support construction]
The shaft steel of the piers were prefabricated and brought in on semi-trailer trucks
The shafts of the piers are stripped and the cross girder is in forms
The steel nearing pier M3 [construction of steel deck truss]
The unsupported channel span four panels beyond the centre [construction of steel deck truss over False Creek]